Customer: Marquardt Gruppe
Project duration: 12 months
Our customer:
The Marquardt Group (hereinafter referred to as »Marquardt«) is a globally active, family-owned company that has successfully established itself in various business sectors since 1925. Since its founding in 1925, the Marquardt Group has evolved into one of the world’s leading experts in mechatronics. Today, more than 11,000 employees work at 22 locations worldwide for Marquardt in the areas of automotive, off-road vehicles, trucks, cleaning equipment, and home technology.
Initial situation:
In 2019, Marquardt purchased an existing factory site with production halls in Ichtershausen, centrally located and easily accessible at Erfurter Kreuz. The company produces mechatronic system solutions there, including functional ambient lighting for vehicle interiors and battery management systems for electric and hybrid vehicles.
The factory site consists of several interconnected halls. The products are manufactured in a production hall over 10,000 square meters in the Ichtershausen industrial area. Long transport routes between the halls and limited space conditions with a ceiling height of just under eight meters have made the provision of materials for production difficult. To meet the required growth rates for the coming years, a flexible and largely automated storage solution had to be found within the limited space.
For production supply and storage of finished goods for OEMs, three fully automated shuttle and container warehouses, as well as autonomous mobile robots (AMR) and several tugger trains, were installed.
As part of the project, HPC implemented highly automated intralogistics processes based on SAP EWM, which, thanks to the EWM-MFS interface integrated into EWM, enables direct connection to three automatic warehouses, the AMRs, and the tugger trains.
To connect the tugger trains, a concept was developed that automatically retrieves material from a container warehouse, sequences it, and buffers it in a sequencing shuttle warehouse for fully automatic tugger train loading.
Project Objectives:
What did HPC accomplish?
Customer benefits:
What were the challenges?
Due to changing requirements resulting from structural conditions, our SAP experts had to design their concept flexibly and adjust it in regular coordination meetings. Simultaneous loading of up to four tugger trains within short time frames was challenging. Despite the challenges, the project duration was maintained, and our client was able to start productive use on schedule. With this automation, Marquardt was able to make material supply more efficient and optimize production processes.